A proposed transfer of 11.74% of the Papua LNG Project from TotalEnergies to ExxonMobil, Santos and ENEOS Xplora has prompted objections from the Gulf Provincial Government (GPG) and PNG Engineering Procurement Construction Manager (PNG EPCM) the PRL 15 Landowners consultant, through separate submissions.
Both submissions ask the Independent Consumer and Competition Commission (ICCC) to examine wider concerns before deciding on the applications.
The proposed transfers would increase ExxonMobil’s interest in the project from about 37.04% to 44%, Santos’s from about 22.84% to 27.13%, and ENEOS Xplora’s from about 2.58% to 3.07%.
The ICCC’s public notice in The National Newspaper dated 5 November 2026 describes the buyers as existing project participants and gives its preliminary view that the transfers are unlikely to materially change competition in relevant PNG markets. It nevertheless invited public comment on possible effects on prices, service quality, customer choice and market entry.
The Gulf Provincial Government says the ICCC should not decide on the applications until it has considered the host provinces and landowners claimed the opportunity to acquire a separate 10% interest. It says earlier requests on this matter have not been answered and argues that the applications do not fully address the issue.
The GPG also wants the ICCC to examine whether the larger interests held by existing participants, particularly ExxonMobil, which also operates the PNG LNG Project could affect competition in areas such as gas marketing, LNG shipping, shared infrastructure and opportunities for local businesses.
It raises a further concern about the short consultation period and asks the ICCC to extend it, obtain more information, and hold a conference involving the applicants, the province and landowner representatives. The GPG asks the Commission to delay or refuse clearance until these matters are addressed, or to impose conditions if it approves the transfers.
PNG EPCM’s submission focuses especially on LNG shipping and Papua New Guinean participation. It refers to government policy and statutory notices issued in 2018, which it says required a state-backed company, Niugini LNG Carrier Limited (NLNGC), to be considered for a role in LNG shipping, including where additional vessels were needed for project expansion.
PNG EPCM alleges that LNG production at the existing PNG LNG Project exceeded its original design capacity and that extra cargoes were transported without NLNGC being given the expected opportunity to participate. It says NLNGC suffered costs and lost business opportunities. These are allegations in the submission; they have not been established by the ICCC in the public notice.
PNG EPCM further argues that the shipping concerns are relevant to the Papua LNG ownership applications because the same companies and sector are involved. It asks the ICCC to defer its decisions, require information about shipping and vessel-charter arrangements, and hold a conference before deciding.
The central question is whether the proposed change in ownership is simply a transfer of interests among existing Papua LNG partners, as the ICCC’s preliminary view suggests, or whether it could also affect competition and access to related opportunities, particularly LNG shipping and participation by the host province, landowners and Papua New Guinean businesses.
The submissions raise connected but distinct concerns which are, GPG’s claimed 10% acquisition opportunity, competition, consultation and local participation, PNG EPCM’s alleged non-compliance with shipping requirements and exclusion of NLNGC, ICCC notice to whether the proposed ownership transfers could substantially lessen competition in PNG markets.
The ICCC’s notice invited submissions by 9 November 2026 which has lapsed. The two groups are asking the Commission to resolve or investigate the broader concerns before granting clearance. The submissions do not establish how the ICCC ultimately decides on the applications or the allegations.