PNG Power confirm that water levels at its Yonki Dam catchment area has reached critical level, due to the
impact of an unusual dry season experienced in the area.
The reduced water levels have forced PNG Power to decrease generating capacity and carry out load
shedding on the Ramu Grid, supplying power to Lae, Madang and the Highlands Provinces.
Currently, Ramu Hydropower Station is operating thirty-five percent (35%) of its total generation capacity,
due to the reduced water levels in the reservoir.
PNG Power is accelerating projects to rehabilitate alternate power generating supplies, to reduce the need
for load shedding. Centres supported by the Ramu grid will supplement power supplies with generators,
where possible.
Load shedding will continue until water levels improve substantially and generating capacity can return to
normal operations.
Independent Power Producers (IPP) are continuing to meet generating capacity shortfalls, especially in Lae
with Posco Daewoo (Munum Power Station) and PNG Forest Products through their Baiune Power Station.
PNG Power relies heavily on clean, hydroelectric power. Presently, 38% of the power generated on the
company’s three grids originates from PNG Power’s hydroelectric facilities.
Unfortunately, however, similar issues are occurring at Sirinumu Dam in Port Moresby, supplying the Rouna
Hydropower Station and the river system feeding the Warangoi Hydropower Station in East New Britain.
PNG Power is appealing to the general public to be mindful of water use and to conserve and ration water
supplies when possible.
The situation is unlikely to improve in the short term